Seawall Repairs, Condominium Roof & Siding Replacement
Contact: David Suder, Treasurer, Kulakane Condominium
c/o Quam Properties Hawaii
5095 Napilihau Street #202, Lahaina, Maui, HI 96761
Telephone: (530) 792-1000
Email: [email protected]
Year: 2014
Project 2: Installation of Cedar Shake Roof and Siding to Main Building and Office
Permits Obtained & Processing Time:
-
Discretionary – permits obtained in 41 days
-
Ministerial – permits obtained in 24 days
Discretionary | Ministerial |
Special Management Area (SMA) Exemption | Flood Development Permit |
Shoreline Setback Approval | Building Permits |
Environmental Assessment Exemption |
Year: 2012
Project 1: Seawall Resurfacing and New Wave Over Wash Lip
Permits Obtained & Processing Time:
-
Discretionary – permits obtained in 120 days
-
Ministerial permits obtained in 53 days
Discretionary | Ministerial |
Special Management Area (SMA) Minor Permit | Flood Development Permit |
Shoreline Setback Approval | Building Permits |
Environmental Assessment Exemption | US Army Corp of Engineers Jurisdictional Determination |
Special Circumstances:
- Obtaineda federal determination that the work did not trigger permits the agency’s permits.
- Obtained concurrence from the State of Hawaii that only County permits were necessary and a Conservation District Use Permit was not required given the scope and manner in which the seawall was being repaired.
- Obtained archival evidence of an existing state-certified shoreline that indicated there were no encroachments onto State property or jurisdiction.